CONCORD GROUP Reference List 2005-2011
In this section the major projects of CONCORD GROUP for the period 2005-2011 are presented.   Legend:
  Current projects, being fulfilled at the present time;
  Fulfilled projects.
   

Turnkey Projects & Revamping

USIMINAS
Ipatinga Plant
Brazil
2010-2012

CO Batteries No.3, No.4

Turn-key reconstruction of peripheral facilities of COB No.3, 4 including the following: coke oven machines, wet quenching objects, coke screening objects, recovery plant, machine room, cooling station, pump station of circulating industrial water and tar desludging unit, power facilities.

USIMINAS
Ipatinga Plant

Brazil
2008-2014

CO Batteries No.3, 4
110 ovens (2 х 55)
H = 6,0 m

Turn-key reconstruction.

ISDEMIR Steel Plant
Turkey
2007-2011

CO Battery No.4
69 ovens,
H = 5,0 m

Turn-key pad-up rebuilding.

PAKISTAN STEEL MILLS
Pakistan
2007-2011

CO Battery No.1
49 ovens,
H = 5,5 m

Turn-key reconstruction.

DUNAFERR
Integrated Steel Plant
Hungary
2008-2010 

Coke Dry Quenching Plant

Turn-key reconstruction.

CZESTOCHOWA NOWA Coke Plant
Poland
2010-2011 

CO Battery No.1
57 ovens,
H = 4,3 m

COB brickwork.

PAKISTAN STEEL MILLS
Pakistan
2007-2010

CO Battery No.2
49 ovens,
H = 5,5 m

Turn-key reconstruction.

ZABRZE Coke Plant
Poland
2006-2008

CO Battery No.1-bis,
88 ovens,
H = 5,0 m

Turn-key construction.

DUNAFERR
Integrated Steel Plant

Hungary
2002-2003 (1-st block)
2005-2006 (2-nd block)

CO Battery No.3
65 ovens,
H = 7,0 m

General Contractor (turn-key) reconstruction of COB No.3.

KREMIKOVTZI AD
Integrated Steel Plant
Bulgaria
2003-2005

CO Batteries No.3, 4
65 ovens,
H = 5.5 m

Adjustment of the thermal and hydraulic regime of the heating of COB No.3. Hot repair of the heating walls of COB No.4 up to the depth of 6 vertical flues on the both sides of the battery.

KRYVORIZHSTAL/
ARCELOR MITTAL STEEL Kryvyi Rih
Ukraine
2005

CO Battery No.3
56 ovens,
H = 6,085 m

Turn-key construction.

KRYVORIZHSTAL/
ARCELOR MITTAL STELL Kryvyi Rih
Ukraine

CO Battery No.4
56 ovens,
H = 6,085 m

Turn-key construction.

KREMIKOVTZI AD
Integrated Steel Plant
Bulgaria
2005

Blast Furnace No.3
V = 1033 m3

Preparation to the first-category overhaul of BF No.3. Development of the reconstruction design. Preparation of the equipment for repair. Delivery of the materials and equipment.
General Contractor. On-the-spot slag-granulation plant for blast furnace.

KREMIKOVTZI AD
Integrated Steel Plant
Bulgaria
 2007

Blast Furnace No.3
V = 1033 m3

Turn-key reconstruction (1st category).

DUNAFERR
Integrated Steel Plant
Hungary
2005

Blast Furnace No.1
V = 960 m3

Preparation to the first-category overhaul of BF No.1. Design works, delivery of refractory materials including carbon blocks.

Hot Repair & Ceramic Welding

DONETSKCOKS
Ukraine
1986–2011

CW No.1-CB No.1, CB No.2
CW No.2-CB No.1.
H = 4,0 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

MAKEEVCOKS
Ukraine
1986-2011

CW No.2, CB No.3.
H = 5,5 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

AVDEEVSKY
By-Product Coke Plant
Ukraine
1987-2011

CB No.5, CB No.6,
CB No.7; CB No.8,
CB No.9, Section No.5,
PCW, Section No.6.
H = 4-7 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

AVDEEVSKY
By-Product Coke Plant
Ukraine
2008-2010, 2011

PCW

Hot repair of refractory masonry using ceramic welding

ZAPOROZHCOKS
Ukraine
1992-2009

CB No.1, CB No.2, CB No.5, CB No.6.
H = 4-7 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

ZAPOROZHCOKS
Ukraine
1992-2005

Section No.1-4.
H = 3,6 m

Hot repair of walls at a depth from 1 to 20 vertical channels using ceramic welding.

ZAPOROZHCOKS
Ukraine
2009-2011

CB No.5, CB No.6.
H = 4 m

Sealing in coking boxes joints.

ZAPOROZHCOKS
Ukraine
2009

CB No.1.
H = 7 m

Sealing of gas flues joints.

ZAPOROZHCOKS
Ukraine
2006-2007

CB No.1.
H = 7 m

CB No.6.
H = 4 m

Rebricking of 105-108 walls from the coke side at a depth of 6 vertical channels on the CB No.1; rebricking of 111-112 walls from the coke side at a depth of 4 vertical channels; rebricking of 626, 627 walls at a depth of 4 vertical channels on the CB No.6. Rebricking of 625 wall from one side at a depth of 2 vertical channels.

ZAPOROZHCOKS
Ukraine
2007-2008

CB No.1.
H = 7 m

Rebricking of 151-158, 161-164 walls from the coke side at a depth of 6 vertical channels.
Total: 72 vertical channels.

ZAPOROZHCOKS
Ukraine
2008

CB No.1, CB No.2.
H = 7 m

Rebricking of 165, 166, 167, 168, 171 walls from the coke side at a depth of 6 vertical channels on the CB No.1.
Total: 30 vertical channels.
Rebricking of 272, 273, 274, 275 walls from the coke side and rebricking of 274, 275 from the machine side at a depth of 4 vertical channels on the CB No.2.
Total: 32 vertical channels.

ZAPOROZHCOKS
Ukraine
2009

CB No.2.
H = 7 m

Rebricking of 201, 202, 203, 204, 205, 206, 207, 212 walls from the machine side at a depth of 4 vertical channels and rebricking of 201, 202, 203, 204, 205, 206, 207, 208, 211, 212 walls from the coke side at a depth of 6 vertical channels.

ZAPOROZHCOKS
Ukraine
2010-2011

 

Rebricking of 224-234 walls from the machine side at a depth of 4 vertical channels and rebricking of 224-234walls from the coke side at a depth of 6 vertical channels.

ALCHEVSKCOKS
Ukraine
1994, 2003, 2005, 2007

CB No.5, CB No.6.
H = 4 m

Hot repair of walls at a depth of 6 vertical channel, in the area of charging door using ceramic welding, repair of coking boxes soles.

ALCHEVSKCOKS
Ukraine
2008-2011

CW No.2.

Hot repair of refractory masonry using ceramic welding and with the application of a milling device. Sealing in coking boxes joints.

YASINOVSKY KHZ
Ukraine
1998-2007

CB No.3.
H = 4 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

YASINOVSKY KHZ
Ukraine
2008

CB No.6.
H = 5.5 m

Sealing in coking boxes joints.

YENAKIEVSKY KHP
Ukraine
2000-2011

CB No.2, CB No.3, CB No.4.
H = 4 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

KHARKOV Coke Plant
Ukraine
1992, 2002, 2003, 2005

CB No.1, CB No.2, CB No.3.
H = 4 m

Hot repair of walls at a depth of 6 vertical channels using ceramic welding..

BAGLEYCOKS
Ukraine
1992, 2002, 2003, 2004

CB No.5.
H = 4 m

Hot repair of walls at a depth of 6 vertical channels, in the area of charging door using ceramic welding.

EVRAZ DMZ Petrovskogo
Ukraine
2002-2006

CB No.3.
H = 4 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

AZOVSTEEL
Integrated Steel Plant
Ukraine
2007

CB No.1, CB No.5.
CW - No.102

Hot repair of refractory masonry using ceramic welding.

EVRAZ-DKHZ
Ukraine
2001

CB No.1.
H = 7 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

CHEREPOVETSKY
Integrated Steel Plant
Russia
1988, 1994

CB No.1, No.2, No.3.
H = 4 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

CHELYABINSKY
Integrated Steel Plant
Russia
1991

CB No.1, CB No.2.
H = 4 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

TRINITS
By-product Coke Plant
Czech Republic
1991

CB No.1.
H = 4 m

Hot repair of walls at a depth of 8 vertical channels using ceramic welding.

DUNAFER-DBK
By-product Coke Plant
Hungary
2005

CB No.3.
H = 4 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

ZABRZE Coke Plant
Poland
2005

CB No.2.
H = 4 m

Hot repair of walls at a depth of 8 vertical channels using ceramic welding.

PSHIYAZN
By-product Coke Plant
Poland
2005

CB No.4, No.3.
H = 4 m

Hot repair of walls at a depth of 4 vertical channels using ceramic welding.

KREMIKOVTZI AD
Integrated Steel Plant
Bulgaria
2004, 2005, 2007

CB No.3, No.4.
H = 4 m

Hot repair of walls at a depth of 6 vertical channels using ceramic welding.

ARCELOR MITTAL Poland
Unit in Krakow
Poland
2006

CB No.3.
H = 5,5 m

Hot repair of walls at a depth of 8 vertical channels using ceramic welding.

AL NASR Co.
for Coke and Chemicals
Egypt
2010-2011

CB No.3, No.2, No.3

Hot repair of heating walls using ceramic welding. Rebricking of heating walls at a depth of 4-8 vertical channels.
Total: 72 vertical channels.