A unique two-stage reconstruction of coke oven battery in operation was carried out.
Preparation works:
Hot repair of 7 ovens before reconstruction of the whole battery in order to stabilize work of by-product coke production.
SCOPE OF CIVIL AND ERECTION WORKS PRO RECONSTRUCTION:
-
arrangement of temporary charge feeding – loading of coal charging car was carried out from the end platform. Charge was fed into bunkers by means of conveyor system;
-
complete re-bricking of the top superstructure;
-
repair of the three upper rows of the inclined flue zone;
-
re-bricking of head part of regenerator walls;
-
replacement of fire grates;
-
replacement of flash plates and door frames;
-
installation of new units for reinforcement lines;
-
replacement of all cross and longitudinal tie rods of oven armoring;
-
replacement of reverse valves and gas and air valves;
-
replacement of hydraulic-assisted stand pipes and industrial pipelines;
-
implementation of automated process control system.